WATTS BAR-2

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
W (4-loop) (ICECND)
Tennessee Valley Authority
Tennessee Valley Authority
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1165 MWe
1165 MWe
1218 MWe
3425 MWt
Construction Start Date First Criticality Date Construction Suspension Date Construction Restart Date
01 Sep, 1973
23 May, 2016
17 Sep, 1985
15 Oct, 2007
First Grid Connection Commercial Operation Date
03 Jun, 2016
N/A

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
NC
NC
NC
NC
NC
Lifetime performance calculated up to year 2015

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
Performance indicators are calculated from the Commercial Operation Date.
NC – cumulative values not calculated when more than 50% of required data is missing in PRIS


Above data are from the PRIS database. Last update on 2016-08-26

Previous  (WATTS BAR-1) (WOLF CREEK)  Next