AKKUYU-1

Under Construction


Reactor Details

Reactor Type Model Owner Operator
PWR
VVER V-392M
Akkuyu Nuclear Joint Stock Company
Akkuyu Nuclear Joint Stock Company
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1114 MWe
1114 MWe
1200 MWe
3200 MWt
Construction Start Date First Criticality Date
03 Apr, 2018
N/A
First Grid Connection Commercial Operation Date
N/A
N/A


Above data are from the PRIS database. Last update on 2018-04-25