China, People's Republic of
Summary
Nuclear Power Reactors
|
28
|
18
|
0
|
0
|
Annual Electrical Power Production
|
4940000.00 GW.h
(Gross, 2012)
|
98200.00 GW.h
(Gross, 2012)
|
|
Electricity Production Share in
2012
|
Reactors
|
Name
|
Type
|
Status
|
Location
|
Reference Unit Power
[MW]
|
Gross Electrical Capacity
[MW]
|
First Grid Connection
|
|
DAYA BAY 1
|
PWR
|
Operational
|
SHENZHEN CITY
|
944
|
984
|
1993-08-31
|
|
DAYA BAY 2
|
PWR
|
Operational
|
SHENZHEN CITY
|
944
|
984
|
1994-02-07
|
|
QINSHAN 2-1
|
PWR
|
Operational
|
Jiaxing
|
610
|
650
|
2002-02-06
|
|
FANGJIASHAN 1
|
PWR
|
Under Construction
|
Jiaxing
|
1000
|
1080
|
|
|
FANGJIASHAN 2
|
PWR
|
Under Construction
|
Jiaxing
|
1000
|
1080
|
|
|
QINSHAN 1
|
PWR
|
Operational
|
Jiaxing
|
298
|
320
|
1991-12-15
|
|
QINSHAN 2-3
|
PWR
|
Operational
|
Jiaxing
|
610
|
650
|
2010-08-01
|
|
QINSHAN 2-4
|
PWR
|
Operational
|
Jiaxing
|
610
|
650
|
2011-11-25
|
|
QINSHAN 2-2
|
PWR
|
Operational
|
Jiaxing
|
610
|
650
|
2004-03-11
|
|
QINSHAN 3-1
|
PHWR
|
Operational
|
Jiaxing
|
650
|
700
|
2002-11-19
|
|
QINSHAN 3-2
|
PHWR
|
Operational
|
Jiaxing
|
650
|
700
|
2003-06-12
|
|
YANGJIANG 1
|
PWR
|
Under Construction
|
Yangjiang
|
1000
|
1080
|
|
|
YANGJIANG 2
|
PWR
|
Under Construction
|
Yangjiang
|
1000
|
1080
|
|
|
YANGJIANG 3
|
PWR
|
Under Construction
|
Yangjiang
|
1000
|
1080
|
|
|
YANGJIANG 4
|
PWR
|
Under Construction
|
Yangjiang
|
1000
|
1080
|
|
|
LING AO 2
|
PWR
|
Operational
|
SHENZEN
|
938
|
990
|
2002-09-14
|
|
LING AO 1
|
PWR
|
Operational
|
SHENZEN
|
938
|
990
|
2002-02-26
|
|
TIANWAN 3
|
PWR
|
Under Construction
|
Lianyungang
|
1050
|
1126
|
|
|
TIANWAN 1
|
PWR
|
Operational
|
Lianyungang
|
990
|
1060
|
2006-05-12
|
|
TIANWAN 2
|
PWR
|
Operational
|
Lianyungang
|
990
|
1060
|
2007-05-14
|
|
LING AO 3
|
PWR
|
Operational
|
SHENZEN
|
1020
|
1080
|
2010-07-15
|
|
LING AO 4
|
PWR
|
Operational
|
SHENZEN
|
1020
|
1080
|
2011-05-03
|
|
SANMEN 1
|
PWR
|
Under Construction
|
Taizhou
|
1000
|
1250
|
|
|
SANMEN 2
|
PWR
|
Under Construction
|
Taizhou
|
1000
|
1250
|
|
|
HONGYANHE 1
|
PWR
|
Operational
|
DALIAN
|
1000
|
1080
|
2013-02-18
|
|
HONGYANHE 2
|
PWR
|
Under Construction
|
DALIAN
|
1000
|
1080
|
|
|
HONGYANHE 3
|
PWR
|
Under Construction
|
DALIAN
|
1000
|
1080
|
|
|
HONGYANHE 4
|
PWR
|
Under Construction
|
DALIAN
|
1000
|
1080
|
|
|
HAIYANG 1
|
PWR
|
Under Construction
|
Haiyang
|
1000
|
1253
|
|
|
HAIYANG 2
|
PWR
|
Under Construction
|
Haiyang
|
1000
|
1253
|
|
|
FUQING 3
|
PWR
|
Under Construction
|
Fuqing
|
1000
|
1080
|
|
|
FUQING 4
|
PWR
|
Under Construction
|
Fuqing
|
1000
|
1080
|
|
|
FUQING 1
|
PWR
|
Under Construction
|
Fuqing
|
1000
|
1080
|
|
|
FUQING 2
|
PWR
|
Under Construction
|
Fuqing
|
1000
|
1080
|
|
|
TAISHAN 1
|
PWR
|
Under Construction
|
Taishan
|
1660
|
1750
|
|
|
TAISHAN 2
|
PWR
|
Under Construction
|
Taishan
|
1660
|
1750
|
|
|
NINGDE 3
|
PWR
|
Under Construction
|
Ningde
|
1000
|
1089
|
|
|
NINGDE 4
|
PWR
|
Under Construction
|
Ningde
|
1000
|
1089
|
|
|
NINGDE 1
|
PWR
|
Operational
|
Ningde
|
1018
|
1089
|
2012-12-28
|
|
NINGDE 2
|
PWR
|
Under Construction
|
Ningde
|
1000
|
1089
|
|
|
CHANGJIANG 1
|
PWR
|
Under Construction
|
Changjiang
|
610
|
650
|
|
|
CHANGJIANG 2
|
PWR
|
Under Construction
|
Changjiang
|
610
|
650
|
|
|
FANGCHENGGANG 1
|
PWR
|
Under Construction
|
Fangchenggang
|
1000
|
1080
|
|
|
FANGCHENGGANG 2
|
PWR
|
Under Construction
|
Fangchenggang
|
1000
|
1080
|
|
|
SHIDAO BAY 1
|
HTGR
|
Under Construction
|
Weihai
|
200
|
211
|
|
|
CEFR
|
FBR
|
Operational
|
Tuoli
|
20
|
25
|
2011-07-21
|
Above data are from the PRIS database. Last update on 2013-05-19