Abstract
This project is part of the On Site Assistance provided by a consortium established between French EDF and Italian Sogin to the Aktau BN-350 NPP, financed by the 1998 budget of Tacis programme of the European Commission (EC). The UKAEA took part in the project that lasted 18 months, since May 2000. This report gives an overview of the outputs of the project: technical studies, study tours and equipment, as well as of interfaces with other international assistance projects to BN-350 NPP decommissioning. Nine technical tasks, addressing the essential topics of nuclear decommissioning, were implemented, aiming to contribute to the elaboration of the decommissioning plan. Topics covered range from plant data collection and regulatory framework analysis to dismantling options studies, including waste management strategy, risk and environmental impact analysis, cost assessment and quality assurance issues. (author)