Unplanned Capability Loss Factor
(UCL)
The purpose of this indicator is to monitor industry progress in minimizing outage time and power reductions that result from unplanned equipment failures or other conditions. This indicator reflects the effectiveness of plant programs and practices in maintaining systems available for safe electrical generation.
Unplanned capability loss factor is defined as the ratio of the unplanned energy losses during a given period of time, to the reference energy generation, expressed as a percentage.
Unplanned energy loss is energy that was not produced during the period because of unplanned shutdowns, outage extensions, or unplanned load reductions due to causes under plant management control. Causes of energy losses are considered to be unplanned if they are not scheduled at least four weeks in advance. Causes considered to be under plant management control are further defined in the clarifying notes.
Reference energy generation is the energy that could be produced if the unit were operated continuously at full power under reference ambient conditions throughout the period. Reference ambient conditions are environmental conditions representative of the annual mean (or typical) ambient conditions for the unit.
The unplanned capability loss factor is determined for each period as shown below:
| Value for a unit, | UCLF(%) = | UEL x 100% |
| REG |
Note: The total unplanned energy loss for the period is the sum of the losses from all unplanned events.
Data for new units is included in the calculation of industry values beginning January 1 of the first calendar year following commercial operation.
(1) Subtracting the actual power level during the event from the power level immediately prior to the event when the power was at or near the reference power level,
(2) Computing the power level reduction that would have occurred with the unit at the reference power level, or
(3) Using historical data from similar events occurring at the reference power level.
For example, if a unit experiences a 10 MW power loss due to an equipment problem while operating at 75 % of the reference power, and it is determined from calculations or from similar events that have occurred at the reference power that the same equipment problem would have resulted in a 20 MW power loss at the reference power level, then 20 MW should be used when computing the energy loss.
The same rule may be used if the change in the start date is decided by plant management, assuming this decision is due to all of the following reasons or circumstances:
The unit is operating in a deregulated environment, and the management decision to modify the planned outage start date is solely to take advantage of economic situations to maximize, on a short term basis, the economic benefit coming from selling the plant electricity output.
This economic benefit can be applied to the entire production system of the Utility, not only to the specific unit under consideration.
UCF + UCLF + PCLF = 100% Over a specific time period
Where:Note: PCLF Replaces the formerly used planned energy unavailability factor (PUF)
|
|
|
| This page was automatically created on 10 Feb 2012, 03:18:34 | |