HONGYANHE-4

Under Construction


Reactor Details

Reactor Type Model Owner Operator
PWR
CPR-1000
Liaoning Hongyanhe Nuclear Power Co. Ltd. (Lhnpc)
Liaoning Hongyanhe Nuclear Power Co. Ltd. (Lhnpc)
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1000 MWe
1000 MWe
1080 MWe
2905 MWt
Construction Start Date First Criticality Date
15 Aug, 2009
N/A
First Grid Connection Commercial Operation Date
N/A
N/A


Above data are from the PRIS database. Last update on 2014-10-30

Previous  (HONGYANHE-3) (LING AO-1)  Next