TIANWAN-1

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
VVER V-428
Jiangsu Nuclear Power Corporation
Jiangsu Nuclear Power Corporation
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
990 MWe
990 MWe
1060 MWe
3000 MWt
Construction Start Date First Criticality Date
20 Oct, 1999
20 Dec, 2005
First Grid Connection Commercial Operation Date
12 May, 2006
17 May, 2007

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
49.43 TW.h
82.8 %
83.0 %
17.2 %
84.8 %
Lifetime performance calculated up to year 2013

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2006 1235.000 1000 2790
2007 5311.000 933 5688 82.7 82.4 82.4 84.8 84.8
2008 6116.160 933 6270 71.4 71.0 75.2 74.6 78.4
2009 6337.710 933 6553 74.8 74.1 74.8 77.5 78.0
2010 7539.590 933 7643 87.2 87.0 78.2 92.2 82.0
2011 7470.080 990 7606 86.8 86.6 80.1 86.1 83.0
2012 7550.160 990 7635 86.9 86.8 81.4 86.8 83.7
2013 7869.050 990 7959 90.9 90.7 82.8 90.7 84.8
Performance indicators are calculated from the Commercial Operation Date.


Above data are from the PRIS database. Last update on 2014-07-24