LING AO-2

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
M310
Lingao Nuclear Power Company Ltd.
Daya Bay Nuclear Power Operations And Management Co,Ltd.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
950 MWe
950 MWe
990 MWe
2905 MWt
Construction Start Date First Criticality Date
28 Nov, 1997
27 Aug, 2002
First Grid Connection Commercial Operation Date
14 Sep, 2002
08 Jan, 2003

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
80.56 TW.h
89.1 %
89.8 %
10.9 %
88.9 %
Lifetime performance calculated up to year 2013

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2002 Data from a trial operation not provided
2003 6934.880 938 7494 85.6 89.9 89.9 84.4 84.4
2004 6669.410 938 7109 80.9 79.8 84.9 81.0 82.7
2005 7530.930 938 8075 92.2 91.2 87.0 91.6 85.7
2006 7660.990 938 8164 93.2 92.1 88.3 93.2 87.6
2007 7215.070 938 7796 89.0 87.8 88.2 87.8 87.6
2008 7077.150 938 7577 86.3 85.2 87.7 85.9 87.3
2009 7433.810 938 8052 91.9 90.9 88.1 90.5 87.8
2010 7505.550 938 8112 92.6 90.8 88.5 91.3 88.2
2011 7734.340 938 8284 94.6 93.7 89.1 94.1 88.9
2012 7474.470 938 8113 92.4 91.0 89.2 90.7 89.1
2013 7261.330 950 7804 89.1 87.9 89.1 87.2 88.9
Performance indicators are calculated from the Commercial Operation Date.


Above data are from the PRIS database. Last update on 2014-11-22