SMOLENSK-3

Operational


Reactor Details

Reactor Type Model Owner Operator
LWGR
RBMK-1000
Joint Stock Company "Concern Rosenergoatom"
Joint Stock Company "Concern Rosenergoatom"
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
925 MWe
925 MWe
1000 MWe
3200 MWt
Construction Start Date First Criticality Date
01 May, 1984
29 Dec, 1989
First Grid Connection Commercial Operation Date
17 Jan, 1990
12 Oct, 1990

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
152.51 TW.h
79.0 %
81.6 %
21.0 %
79.4 %
Lifetime performance calculated up to year 2013

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
1990 4570.760 925 6767 100.0 99.1 99.1 101.2 101.2
1991 6561.740 925 7338 83.8 80.9 84.5 81.0 85.0
1992 6866.560 925 7515 85.6 83.9 84.2 84.5 84.8
1993 6595.990 925 7419 84.7 81.4 83.4 81.4 83.8
1994 5513.660 925 6701 76.5 72.5 80.8 68.0 80.1
1995 5090.970 925 5844 66.7 63.2 77.5 62.8 76.8
1996 6496.640 925 7268 82.7 80.8 78.0 80.0 77.3
1997 5559.270 925 6469 73.8 69.3 76.8 68.6 76.1
1998 4575.890 925 6162 70.3 57.5 74.5 56.5 73.7
1999 6410.980 925 7063 80.6 78.2 74.9 79.1 74.3
2000 6970.480 925 7542 85.9 84.6 75.8 85.8 75.4
2001 6951.720 925 7823 89.3 85.4 76.7 85.8 76.4
2002 7204.900 925 7831 89.4 87.7 77.6 88.9 77.4
2003 7038.230 925 7697 87.9 86.3 78.2 86.9 78.1
2004 7085.740 925 7765 88.4 86.9 78.8 87.2 78.7
2005 7303.680 925 8192 93.5 90.4 79.6 90.1 79.5
2006 4942.960 925 5631 64.3 60.7 78.4 61.0 78.3
2007 7566.250 925 8247 94.1 92.5 79.2 93.4 79.2
2008 5093.440 925 5396 61.4 61.2 78.2 62.7 78.3
2009 6082.980 925 6706 76.6 74.3 78.0 75.1 78.1
2010 7738.820 925 8233 94.0 93.6 78.8 95.5 79.0
2011 6241.790 925 6579 75.1 74.0 78.6 77.0 78.9
2012 5845.230 925 6279 71.5 70.6 78.2 71.9 78.6
2013 7942.170 925 8471 96.7 95.1 79.0 98.0 79.4
Performance indicators are calculated from the Commercial Operation Date.


Above data are from the PRIS database. Last update on 2014-11-23