RAJASTHAN-5

Operational


Reactor Details

Reactor Type Model Owner Operator
PHWR
Horizontal Pressure Tube type
Nuclear Power Corporation Of India Ltd.
Nuclear Power Corporation Of India Ltd.
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
202 MWe
202 MWe
220 MWe
801 MWt
Construction Start Date First Criticality Date
18 Sep, 2002
24 Nov, 2009
First Grid Connection Commercial Operation Date
22 Dec, 2009
04 Feb, 2010

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
6.58 TW.h
92.2 %
92.8 %
7.8 %
94.9 %
Lifetime performance calculated up to year 2013

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2009 0.200 202 1
2010 1406.170 202 7158 89.3 85.7 85.7 86.8 86.8
2011 1741.800 202 8325 95.0 94.9 90.5 98.4 92.9
2012 1587.810 202 7590 86.4 87.5 89.5 89.5 91.7
2013 1842.260 202 8760 100.0 100.0 92.2 104.1 94.9
Performance indicators are calculated from the Commercial Operation Date.


Above data are from the PRIS database. Last update on 2014-08-20

Previous  (RAJASTHAN-4) (RAJASTHAN-6)  Next