Waste Technology Section

International Decommissioning Network (IDN)


New Stuff



Announcements


The decommissioning of the Danish Reactor 2 – DR 2 – was completed in 2008. The final report approved by the Danish Nuclear Licensing authorities has been translated to English and is now available through the following link:

http://dekom.dk/publikationer/DR_2_Final_report_EN/

Enjoy reading and feel free to comment or ask questions concerning the report.


The Annual Forum for Regulators and Operators in the Field of Decommissioning: International Decommissioning Network (IDN) Activities and Other Major Decommissioning Initiatives will be held at the IAEA's Headquarters in Vienna, from 2 to 6 November 2009

The Forum will consist of two parts. Part 1, the annual meeting of the 'International Decommissioning Network' (IDN) and Part 2, a special topical session on 'Communications with Decommissioning Stakeholders'. The objective of Part 1 will be to inform and seek input from senior representatives of organizations from Member States concerning the progress made in decommissioning, especially aspects related to the goals and objectives of the IDN. In Part 2, the main elements of a successful public communications programme concerning a decommissioning project will be addressed and the lessons learned from relevant experience summarized and reinforced.

Click for the Terms of Reference


CEA (France) – Video Demonstrations

Dismantling Nuclear Facilities: The AT1 at La Hague Site was a pilot facility built to address the treatment of nuclear waste. Its objective was to reprocess spent fuel elements from fast breeder reactors. After ten years of operation and reprocessing of spent fuel the facility was shut down in June 1979. Though some of the operations were carried out in the traditional method using direct manual work, many of the assignments required the use of new techniques due to the high irradiation levels which were found. One of the problems faced during the dismantling process concerned how to deal with the "blind cells" where manual intervention was needed. Not only a pilot unit for reprocessing, AT1 is also considered to be a pilot unit in dismantling as well. Although a variety of problems were encountered, the dismantling of AT1 was a success. Download Video (Warning - video is 109MB) or Download the Technical Report

Dismantling RM2 (Radio-Metallurgy Laboratory): This facility was built in the late 60ÿs to carry out destructive examinations of samples of irradiated fuel, very rich in plutonium and was in operation from 1967 to 1983. The aim was to extract the fuel from its protective covering, cut it into strips and put them through various tests. The decommissioning objective was to reduce the installation to its initial state. A world first! The operation was carried out in two stages: first, from 1990 to 1996, it was cleaned and radioactivity removed and then dismantled. In the video these two procedures can be seen in detail. Decision has been taken to demolish the civil works of all the concrete cells, this work will start in 2008. Download Video

Dismantling The Oris Cells 22, 23 and 24 : These cells were the prototypes for industrial production of sources. They were built in the mid 60`s and remained in use until 1972. They produced Cesium 137 and Strontium 90 sources. One of the challenges shown in this tape is that these cells covered a surface area of some 150m2 on an active production site. They were shut down in 1973 and taken permanently out of service in 1987 and remained in disuse until 1987 when a cleaning campaign was launched to dismantle the effluent storage tanks located under the cells. The team encountered various problems such as finding a high level of radioactivity inside the enclosures which restricted the dismantling operatorsÿ access. Another issue addressed in the tape is that the work area, located inside the production site, could not interfere with the work of the staff located nearby, during the evacuation of the waste and decontamination of the inside of the enclosures. The dismantling was completed in 1994.
Download Video

Credits: These video demonstrations were produced by the French Atomic Energy Commission, Nuclear Energy Directorate, Clean-up Directorate and made available by the CEA to the IAEA for information purposes. Many thanks to Jean-Guy Nokhamzon of the CEA for locating these very useful videos!



Miscellaneous

Dr. Axel Bäcker (EWN, Germany) has offered to take us through the difficult manpower transition issues associated with decommissioning on the Greifswald NPP with his presentation on: Social aspects of decommissioning - Workforce redeployment for decommissioning . Please look at these and email Ms. Andressa Junger if you would like to take part in a teleconference on this topic.

A comparison of laser-cutting techniques and their performance seen in Japan As provided by Dr. Satoshi Yanagihara, JAEA Lasercutting.pdf

Interesting facts and comparisons regarding laser-cutting, with thanks to Andrew Szilagyi http://www.teskolaser.com/waterjet_cutting.html

The "Brochure" showing the overall decommissioning activities of the Agency at a glance

IDN Presentation (Overview)

Decommissioning documents available from the Agency

Matrix that shows the correspondence between common decommissioning topics and the Agency decommissioning documents (Very much still a work in progress but useful for planning)

Considerations in dismantlement of the ASTRA biological shield
(Preliminary input to a CRP by Dr Franz Meyer, Seibersdorf.)